PRINCE2 Processes - The PRINCE2 Process Model

PRINCE2 is a process-based approach for project management providing an easily tailored, and scaleable method for the management of all types of projects.

Each process is defined with its key inputs and outputs together with the specific objectives to be achieved and activities to be carried out.

Below you will find a diagram and subsequent explanation of the PRINCE2 processes to help guide you when managing projects with PRINCE2.

Leading Accredited Training Organistion ILX Group also provide a free comprehensive PRINCE2 process model poster available for you to download and use as a quick reference on your desk or wall!

See the PRINCE2 download centre for many more useful PRINCE2 resources, available for free from ILX Group.

If you require PRINCE2 training there are two PRINCE2 qualification levels you can get accredited for: PRINCE2 Foundation and PRINCE2 Practitioner.

PRINCE2 Foundation level is for those with a requirement to learn the basics and terminology of PRINCE2. A PRINCE2 Foundation qualification can be reached with ILX's renowned PRINCE2 Foundation computer based training package or a 3-day PRINCE2 Foundation tutor-led classroom course.

PRINCE2 Practitioner is the highest level qualification and is suitable for those with the need to manage projects within a PRINCE2 environment. A PRINCE2 Practitioner qualification can be reached with the ILX combined PRINCE2 Foundation and Practitioner blended package or a combined PRINCE2 Foundation and Practitioner 5-day tutor-led classroom course.

Click on one of the PRINCE2 Processes in the below PRINCE2 Process Model Diagram to see a summary.

PRINCE2 Process Model Diagram PRINCE2 Process Model - Directing a Project PRINCE2 Process Model - Starting up a Project PRINCE2 Process Model - Initiating a Project PRINCE2 Process Model - Controlling a Stage PRINCE2 Process Model - Managing Stage Boundaries PRINCE2 Process Model - Closing a Project PRINCE2 Process Model - Managing Stage Boundaries PRINCE2 Process Model - Managing Product Delivery

top of page

Directing a Project

Directing a Project runs from the start-up of the project until its closure. This process is aimed at the Project Board. The Project Board manages and monitors via reports and controls through a number of decision points.

The key processes for the Project Board break into four main areas:

top of page

Starting up a Project

This is the first process in PRINCE2. It is a pre-project process, designed to ensure that the pre-requisites for initiating the project are in place.

The process expects the existence of a Project Mandate which defines in high level terms the reason for the project and what outcome is sought. Starting up a Project should be very short.

The work of the process is built around the production of three elements:

top of page

Initiating a Project

The objectives of Initiating a Project are to:

top of page

Managing Stage Boundaries

This process provides the Project Board with key decision points on whether to continue with the project or not.

The objectives of the process are to:

top of page

Controlling a Stage

This process describes the monitoring and control activities of the Project Manager involved in ensuring that a stage stays on course and reacts to unexpected events. The process forms the core of the Project Manager's effort on the project, being the process which handles day-to-day management of the project.

Throughout a stage there will be a cycle consisting of:

This process covers these activities, together with the on-going work of risk management and change control.

top of page

Managing Product Delivery

The objective of this process is to ensure that planned products are created and delivered by:

top of page

Closing a Project

The purpose of this process is to execute a controlled close to the project.

The process covers the Project Manager's work to wrap up the project either at its end or at premature close.

Most of the work is to prepare input to the Project Board to obtain its confirmation that the project may close.

The objectives of Closing a Project are therefore to:

top of page

Planning

PRINCE2 recommends three levels of plan to reflect the needs of the different management levels involved in the project, stage and team.

Planning is a repeatable process and its activities are included within the seven main PRINCE2 processes, as appropriate. Information about plans and how to plan can be found in the Plans Theme section of the PRINCE2 Manual.

The activities of planning are :-

PRINCE2 uses a technique known as ‘Product based planning’ which requires four activities :-

These four activities are performed within the ‘Define and analyse the products’ activity above.


top of page

+44 (0)1270 611600
PRINCE2 Training Quote
PRINCE2 Downloads

PRINCE2® is a registered trade mark of the Cabinet Office.

P3M3® is a registered trade mark of the Cabinet Office.

The Swirl logo™ is a trade mark of the Cabinet Office.